2001 - Congress recognizes LA 1 as a “High Priority Corridor."

2004 - All environmental permits for the LA 1 Project are completed.

2006 - Construction begins on Phases 1B,1C, and 1D of the LA 1 Project - a two-lane overpass at Leeville, interchanges and toll facility

2007 - Construction begins on Phase 1A of the LA 1 Project - a two-lane elevated highway between Leeville and Port Fourchon

2011 - Entire Phase 1 of the LA 1 Project completed and new Leeville overpass and elevated highway to Port Fourchon opens to traffic.

2011 - A Department of Homeland Security study estimates up to a $7.8 billion loss of Gross Domestic Product should the 7.1-mile section of at-grade LA 1 between Golden Meadow and Leeville be impassable for 90 days. 

 

200 OK

OK

The server encountered an internal error or misconfiguration and was unable to complete your request.

Please contact the server administrator, [no address given] and inform them of the time the error occurred, and anything you might have done that may have caused the error.

More information about this error may be available in the server error log.